T1 - The impact of the recent economic recession on the operation of the NEC contract in Northern Ireland
AU - Brooks, Tara
AU - Spillane, John
AU - Tansey, Paul
AU - Hendron, Caroline
N1 - Publisher Copyright:
© 2016 Informa UK Limited, trading as Taylor & Francis Group.
PY - 2016/6/2
Y1 - 2016/6/2
N2 - In May 2006, the New Engineering Contract (NEC) contract was introduced as the preferred contract for Northern Ireland public sector works. This was subsequently followed by the 2007 economic crash and ensuing recession, which continues to affect the Northern Ireland Construction Industry, to a greater extent than the remainder of the United Kingdom. However, use of the NEC contract has increased during this period, particularly in the public sector. There has been debate in the literature regarding the impact of the NEC contract on adversarial behaviour, but little consideration of the impact of external economic factors on the use of the NEC contract. Using a sequential mixed method approach, the study aims to fill this gap in knowledge through examination of the impact the economic downturn has had on the operation of the NEC contract in Northern Ireland. Qualitative and quantitative findings show that the demands placed by the NEC contract, and the effects of the economic recession, have exerted opposing forces on contract implementation, thus hindering its execution. The findings can lead to a deeper understanding, in the context of both industry and academia, of situations where a lack of resources may negatively impact the operation of the NEC contract.
AB - In May 2006, the New Engineering Contract (NEC) contract was introduced as the preferred contract for Northern Ireland public sector works. This was subsequently followed by the 2007 economic crash and ensuing recession, which continues to affect the Northern Ireland Construction Industry, to a greater extent than the remainder of the United Kingdom. However, use of the NEC contract has increased during this period, particularly in the public sector. There has been debate in the literature regarding the impact of the NEC contract on adversarial behaviour, but little consideration of the impact of external economic factors on the use of the NEC contract. Using a sequential mixed method approach, the study aims to fill this gap in knowledge through examination of the impact the economic downturn has had on the operation of the NEC contract in Northern Ireland. Qualitative and quantitative findings show that the demands placed by the NEC contract, and the effects of the economic recession, have exerted opposing forces on contract implementation, thus hindering its execution. The findings can lead to a deeper understanding, in the context of both industry and academia, of situations where a lack of resources may negatively impact the operation of the NEC contract.
KW - Contract administration
KW - contractual relations
KW - Northern Ireland
KW - recession
UR - http://www.scopus.com/inward/record.url?scp=84978116680&partnerID=8YFLogxK
U2 - 10.1080/01446193.2016.1194522
DO - 10.1080/01446193.2016.1194522
M3 - Article
AN - SCOPUS:84978116680
SN - 0144-6193
VL - 34
SP - 393
EP - 417
JO - Construction Management and Economics
JF - Construction Management and Economics
IS - 6
ER -